Note: Microsoft Project for the web will soon become Microsoft Planner. You can continue using most of the Project for the web capabilities in the new Planner once it's rolled out to your organization. Learn more about the new Planner in Frequently asked questions about Planner and Planner help & learning.

​​​​​​​ Your browser does not support video. Install Microsoft Silverlight, Adobe Flash Player, or Internet Explorer 9.

Tip: Video not in your language? Try selecting Closed Captions Closed captions button .

Try it!

To build a project, first use Grid view to add tasks, assign tasks, and add a duration. Then use Timeline view to add dependencies.

Use Grid view to add tasks, assign tasks, and add a duration

  1. At the top of your project, select Grid view.

  2. Select Add new task and type a task name.

  3. To assign the task, click in the box under Assigned to and type a name or select someone from the drop-down.

  4. To add a duration, click the box under Duration, and enter an option.

Use Timeline view to add dependencies

  1. Select Timeline view.

  2. To connect individual tasks with dependencies, drag the connector between tasks to show which tasks can only start when others are finished.

    Or, use the Shift button to select several tasks, right-click, and select Add dependency.

As time estimates change, drag the task bars to update your project.

Want more?

Project training

Project help center

ต้องการความช่วยเหลือเพิ่มเติมหรือไม่

ต้องการตัวเลือกเพิ่มเติมหรือไม่

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.