Applies ToProject Server 2016 Project Server 2013 Project Online

< More Project help

This topic is for organizations that track time and task progress using separate views.    Not sure if this is for you?

Sometimes the number of hours that the schedule has left for a task doesn’t match up with the amount of time you think you’ll be spending to finish that task. For example, after completing 20 of the 40 scheduled hours for a task, you may feel like you have more than 20 hours of work left to do before the task is finished. By submitting your estimated remaining work to your project manager, you are communicating task progress.

  1. Click Tasks on the Quick Launch.

    Tasks view on the Quick Launch

  2. Update your tasks.

    In the grid, fill out the Remaining Work column.

    Remaining Work column

    If you don’t see the task that you want to update, click Tasks > Add Row.

    Add Row

    If you’re completely done with a task, select the check box for the task, and then click Task > Mark Complete. Remaining work is set to 0 hours.

    Mark Complete

  3. Send your updates to the project managers for your tasks.

    If you’re ready to send all of your updates, click Tasks > Send Status > All Tasks.

    All Tasks

    If you only want to submit some of your updates, select the check box for each task, and then click Tasks > Send Status > Selected Tasks.

    Selected Tasks

    Tip:  Not ready to submit? If you aren’t ready to send your remaining work to the project manager, click Tasks > Save to save your updates and submit them later.

    Save

Bạn cần thêm trợ giúp?

Bạn muốn xem các tùy chọn khác?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.