Applies ToỨng dụng khách Project Online trên Máy tính để bàn Project Standard 2024 Project Professional 2021 Project Standard 2021 Project Professional 2019 Project Standard 2019 Project Professional 2016 Project Standard 2016 Project Professional 2013 Project Standard 2013

Data Type    Duration

Entry Type    Calculated

Description    The Total Slack field contains the amount of time a task's finish date can be delayed without delaying the project's finish date.

How Calculated    Microsoft Office Project bases its calculations of total slack on comparisons of the dates in the Early Start, Early Finish, Late Start, and Late Finish fields for the task, which in turn take into account the dates for any successor tasks. Total slack is calculated as the smaller value of the Late Finish minus the Early Finish field, and the Late Start minus the Early Start field.

Best Uses    Use the Total Slack field to determine whether the task has any time available for a delay. This can be useful if a resource needs more time on a task, or if you want to assign a resource to another task. You can also use the Total Slack field to determine how to recover a schedule that's slipping.

Example    You have received suggestions from management about some additional tasks to add to the project. You have agreed to review the schedule to see whether there is any slack to accommodate any new tasks. You add the Total Slack field to the task sheet and look for sizable positive numbers, which indicate there is some extra time available in the schedule.

Remarks    Total slack can be positive or negative. If total slack is a positive number, it indicates the amount of time that the task can be delayed without delaying the project finish date. If total slack is a negative number, it indicates the amount of time that must be saved so that the project finish date is not delayed. Negative slack indicates that there is not enough time scheduled for the task and is usually caused by constraint dates.

The behavior of total slack can differ depending on the link type. For example, if you're working with a Start-to-Start task relationship, the total slack can change when you enter progress on the predecessor task. With progress entered on the predecessor task, the start date of the successor task is now known and becomes part of the total slack calculation.

Bạn cần thêm trợ giúp?

Bạn muốn xem các tùy chọn khác?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.