Data Type Date
Entry Type Calculated
Description The Preleveled Finish field contains the finish date of a task as it was before resource leveling was done.
How Calculated Before Microsoft Office Project levels resources, it saves the current finish dates for tasks in the Preleveled Finish field.
Best Uses Add the Preleveled Finish field to a task sheet if you want to examine the effects of resource leveling on your project's finish dates.
Example Two resources in your schedule were overloaded, so you applied resource leveling to the project. You now want to see the effects of the leveling on your task finish dates. You add the Preleveled Finish field next to the Finish field in the Task Sheet view to make your comparisons.
Remarks You can use the Leveling Gantt view to see the preleveled finish date shown with the preleveled Gantt bars. Once you've leveled the project, specific tasks will have preleveled finish dates that you cannot remove.