Evaluate resource capacity in Project Online
Applies ToProject Server 2016 Project Online

When you need to know if resources are overbooked, you can use the Capacity Planning view, in the Resource Center, to compare how many hours a resource is able to put in versus how many hours they’re needed on projects.

In the Resource Center, select the check box for each resource you want to review, and then click Resources > Capacity Planning.

Choose Capacity Planning on the Resources tab

Choose Availability > View > Capacity and Engagements Heatmap.

Choose the Capacity and Engagements Heatmap from the View list

In this view:

  • Green means things are good. The resource’s engaged time is roughly the same as the resource’s overall capacity.

  • Blue shows where a resource is underused. The resource’s engaged time is significantly lower than the resource’s overall capacity, and should be given more work.

  • Red shows where a resource is overextended. The resource’s engaged time is significantly higher than the resource’s overall capacity, and should have some work either reassigned to someone else, or moved to a less-busy timeframe.

In the following example, we see two resources: Justin and Leona. Justin is underused during the week of 11/2, because he’s only engaged for 8 hours of work, and Leona is overextended during the week of 11/9, because she’s engaged for a total of 80 hours of work across two projects.

Two resource rows with heatmap coloring

Justin should be added to more work to get him closer to his 40-hour capacity, and Leona should have some of her work reassigned or pushed out so that she has a reasonable workload for her 40-hour capacity.

For more detail about what work each resource is doing, click Availability > Resource Assignments.

Choose Resource Assignments on the Availability tab

The Resource Assignments view shows task assignments, dates, actual work, and remaining work. With this level of detail, you have the right information to make suggestions on how the resources could be used more effectively.

Want to change the view?

There are several things you can change in this view.

Change this...

By doing this...

Which boxes are highlighted with red or blue

Adjust the percentages in Availability > Thresholds.

Which way columns are shown in the grid

Adjust the Timescale in Availability > Filters.

Which way work is shown in the grid

Adjust the Work Units in Availability > Filters.

Which dates are shown in the grid

Click Set Date Range in Availability > Date Range.

Whether to show engagements that aren't accepted yet

Select the Include proposed bookings check box in Availability > Filters.

Da li vam je potrebna dodatna pomoć?

Želite još opcija?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.