The Budget Cost fields are used to enter or review budget costs for budget cost resources. Budget resources are assigned only to the project summary task. You can use the Budget Cost fields to compare the current budgeted costs with the planned or actual costs for the project.
There are several categories of Budget Cost fields.
Budget Cost (task field)
Data Type Currency
Entry Type Calculated
How Calculated When you assign a cost resource that is a budget resource to a project summary task, and then enter a budget amount for the cost resource in either the Task Usage or Resource Usage view, Microsoft Project rolls up the total amount to the project summary task.
This information can then be used to review the overall budget cost information for the project. If the project is part of a master project or portfolio of projects, the project summary budget cost information can be compared and analyzed against other projects. The project summary task of the master project includes the value of its own budget resources plus the sum of the budget resources of its inserted projects.
Best Uses Add the Budget Cost field to a task view and show the project summary task when you want to review the total budget for cost resources. After you start tracking progress in your project plan, you can use the Budget Cost field to compare your budgeted costs against your actual costs.
Example With a budget of $15,000 for travel for a three-month project, you have identified "Travel" as a cost resource and a budget resource. You've assigned this cost resource to the project summary task, and entered the budget amount for travel in the Task Usage view. As work on the project continues, you enter actual progress information in the project plan. You compare any variances between your planned costs and actual costs to ensure that you're on track and to make any necessary adjustments.
Remarks You can only enter information in the Budget Cost field for cost resources that are budget resources. (For work and material resources that are budget resources, you can enter information in the Budget Work fields.)
Budget Cost (resource field)
Data Type Currency
Entry Type Calculated
How Calculated When you assign a cost resource that is a budget resource to a project summary task, and then enter a budget amount for the cost resource in either the Task Usage or Resource Usage view, Project copies that budget amount to the Budget Cost resource field.
Best Uses Add the Budget Cost field to a resource view when you want to review the budget for cost resources, or to compare the budgets of cost resources to each other.
Example With a budget of $15,000 for travel for a three-month project, you have identified "Travel" as a cost resource and a budget resource. You've assigned this cost resource to the project summary task, and entered the budget amount for travel in the Task Usage view. When you add the Budget Cost field to the resource sheet, you see that the "Travel" cost resource reflects this budget of $15,000.
Remarks You can only enter information in the Budget Cost field for cost resources that are budget resources. (For work and material resources that are budget resources, you can enter information in the Budget Work fields.)
Budget Cost (assignment field)
Data Type Currency
Entry Type Entered
Best Uses Add the Budget Cost field to the Task Usage or Resource Usage view when you want to enter the budget amount for cost resources on assignments, or when you want to compare the budgets of cost resources to one another.
Example With a budget of $15,000 for travel for a three-month project, you have identified "Travel" as a cost resource and a budget resource. You've assigned this cost resource to the project summary task. You can now enter the lump-sum budget amount for travel in the sheet portion of the Task Usage view.
Remarks You can only enter information in the Budget Cost field for cost resources that are budget resources. (For work and material resources that are budget resources, you can enter information in the Budget Work fields.)
Budget Cost (task-timephased field)
Data Type Currency
Entry Type Calculated
How Calculated When you assign a cost resource that is a budget resource to a project summary task, and then enter a budget amount for the cost resource in either the Task Usage or Resource Usage view, Project rolls down the total amount to the task-timephased level.
Best Uses You can show the Budget Cost field in the timesheet portion of the Task Usage view by adding it in the Detail Styles dialog box. This shows the budget cost for the task and assignment(s) spread out over time.
After you start tracking progress in your project plan, you can use the Budget Cost field to compare your budgeted costs against your actual costs.
Example With a budget of $15,000 for travel for a three-month project, you have identified "Travel" as a cost resource and a budget resource. You've assigned this cost resource to the project summary task, and entered the budget amount for travel on the assignment in the Task Usage view. As work on the project continues, you enter actual progress information in the project plan. You compare any variances between your planned timephased costs and actual timephased costs to ensure that you're on track and to make any necessary adjustments.
Remarks You can only enter information in the Budget Cost field for cost resources that are budget resources. (For work and material resources that are budget resources, you can enter information in the Budget Work fields.)
Budget Cost (resource-timephased field)
Data Type Currency
Entry Type Calculated
How Calculated When you assign a cost resource that is a budget resource to a project summary task, and then enter a budget amount for the cost resource in either the Task Usage or Resource Usage view, Project rolls down the total amount to the resource-timephased level.
Best Uses You can show the Budget Cost field in the timesheet portion of the Resource Usage view by adding it in the Detail Styles dialog box. This shows the budget cost for the resource and assignment(s) spread out over time.
Example With a budget of $15,000 for travel for a three-month project, you have identified "Travel" as a cost resource and a budget resource. You've assigned this cost resource to the project summary task, and entered the budget amount for travel on the assignment in the Resource Usage view. As work on the project continues, you enter actual progress information in the project plan. You compare any variances between your planned timephased costs and actual timephased costs to ensure that you're on track and to make any necessary adjustments.
Remarks You can only enter information in the Budget Cost field for cost resources that are budget resources. (For work and material resources that are budget resources, you can enter information in the Budget Work fields.)
Budget Cost (assignment-timephased field)
Data Type Currency
Entry Type Entered
Best Uses You can show the Budget Cost field in the timesheet portion of the Task Usage or Resource Usage view by adding it in the Detail Styles dialog box. You can now enter or review the budget cost for the assignment spread out over time.
Example With a budget of $15,000 for travel for a three-month project, you have identified "Travel" as a cost resource and a budget resource. You've assigned this cost resource to the project summary task. You can now enter timephased or contoured budget amount for travel in the timesheet portion of the Task Usage or Resource Usage view.
Remarks You can only enter information in the Budget Cost field for cost resources that are budget resources. (For work and material resources that are budget resources, you can enter information in the Budget Work fields.)