Applies ToProject Online datora klients Project Standard 2024 Project Professional 2021 Project Standard 2021 Project Professional 2019 Project Standard 2019 Project Professional 2016 Project Standard 2016

Usually, you report your project’s progress on a day you set— the status date, to use project management-speak. For example, if you want sales report figures for last month, you set the status date to the last day of that month. Or, if progress reports are due Friday, but were sent in late, you might set the status date back to Friday before reporting on progress information.

The status date is almost never the current date, so you need to set it:

  1. Choose Project > Status Date.Set the status date for a project image

  2. Select the new status date. To set the status date back to the current date, either enter the current date, or enter NA in the date field.

View the status date on the Gantt Chart

  1. On the Gantt Chart, choose Format > Gridlines.

  2. Under Line to change, pick Status Date, and then select a line style and color.

Change the status date image

How does the status date affect progress updates?

When you enter progress as percent complete or actual work to date, Project uses the status date to determine where to place actual work and where to schedule remaining work. You can modify the default settings for how the status date is used for placing actual work and remaining work where you want, particularly when assignments are completed earlier or later than scheduled.

To modify the default settings, choose File > Options > Advanced, and scroll to the Calculation options for this project section. 

  • Move end of completed parts after status date back to status date

    Consider tasks that are scheduled after the status date, and have actuals entered against them. If the Move end of completed parts after status date back to status date check box is selected, then if a task is scheduled after the status date and you enter actuals against it, Project moves the actual, completed portion of the task so that the completed work ends on the status date and any remaining work remains scheduled to begin in the future. Therefore, if the status date is set to today, and you enter actuals, the work is assumed to finish today, not in the future. But the remaining work is not expected to start until the future:

    Move end of completed task parts after status date back to status date

  • And move start of remaining parts back to status date 

    If the Move start of remaining parts before status data forward to status date check box is selected, you can also select the And move start of remaining parts back to status date check box. With both check boxes selected, Project moves the entire task around the status date to show that work was done on the task and completed as of the status date and remaining work is continuing as of the status date:

    And move start of remaining parts back to status date

  • Move start of remaining parts before status data forward to status date

    Consider tasks that are scheduled before the status date and that have actuals entered against them. If the Move start of remaining parts before status data forward to status date check box is selected, then if a task is scheduled before the status date and you enter actuals against it, Project leaves the actual portion of the task as scheduled, but moves any remaining work to the status date. Therefore, if the status date is set to today and you enter actuals, the work is assumed to have been completed when it was scheduled, but it is assumed that the remaining work will begin immediately instead of in the past (before the status date):

    Move start of remaining parts before status data forward to status date

  • And move end of completed parts forward to status date

    If the Move start of remaining parts before status date forward to status date check box is selected, you can also select the And move end of completed parts forward to status date check box. With both check boxes selected, Project moves the entire task around the status date, to show that work was done on the task and completed as of the status date and that remaining work is continuing as of the status date:

    And move end of completed parts forward to status date

These settings are particularly useful when you want to see "ahead of schedule" progress lines. They're also useful for changing how earned value is accrued.

If you change these settings, Project does not move the actual or remaining work at all; work remains where it was originally scheduled, even if you report that the work was completed several weeks earlier than scheduled.

Note: These settings do not control the placement of actual and remaining work when you track progress by entering actual work by time period.

How does the status date affect earned value?

Certain earned value costs are calculated as of the status date. For example, the budgeted cost of work scheduled (BCWS) is the portion of the cost that is planned to be spent on a task between the task's start date and the status date. For example, the total planned budget for a four-day task is $100, and it starts on a Monday. If the status date is set to the following Wednesday, the BCWS is $75. When you change the status date, the earned value calculations reflect costs up to and including the status date.

How does the status date affect calculations for progress lines?

If you use progress lines to display progress information, you can display progress lines for the status date, current date, or regular intervals. To be sure that progress lines are shown correctly, choose File > Options > Advanced, and scroll to the Calculation options for this project section. Select the Edits to total task % complete will be spread to the status date check box. This setting ensures that Project evenly spreads the work reported through percentage complete up to the status date. Then, when you display progress lines, the progress lines reflect the likely progress of work on any given date.

Nepieciešama papildu palīdzība?

Vēlaties vairāk opciju?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.