Applies ToProject Online datora klients Project Professional 2021 Project Standard 2021 Project Professional 2019 Project Standard 2019 Project Professional 2016 Project Standard 2016 Project Professional 2013 Project Standard 2013

Data Type    Date

Entry Type    Calculated

Description    The Finish field shows the date when a resource is scheduled to complete work on all assigned tasks.

How Calculated    Microsoft Office Project calculates the resource finish date as the latest finish date of all assignments for the resource.

Best Uses    Add the Finish field to a resource view to see or filter for latest finish dates for resources.

Example    You need to see when Jamie is scheduled to finish the last of 10 assigned tasks. In the Resource Sheet view, you add the Finish field. You see the latest scheduled finish date of all of Jamie's assignments.

Nepieciešama papildu palīdzība?

Vēlaties vairāk opciju?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.