Applies ToProject Online datora klients Project Professional 2021 Project Standard 2021 Project Professional 2019 Project Standard 2019 Project Professional 2016 Project Standard 2016 Project Professional 2013 Project Standard 2013

Data Type    Date

Entry Type    Calculated

Description    The Created field contains the date and time when a resource was added to the project.

How Calculated    Microsoft Office Project assigns the current date to this field based on the current date set in Microsoft Windows.

Best Uses    Add the Created field to a resource view when you need to see when resources were added to the project. This can be particularly useful if you have a large number of resources and you want to filter for resources added to the project within a certain time frame.

Example    You need to update the billing code for all the resources that were added to your project after June 30. Use the Created After filter to view all resources with a date in the Created field that falls after June 30.

Nepieciešama papildu palīdzība?

Vēlaties vairāk opciju?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.