Applies To„Project Online“ kompiuterio klientas Project Professional 2021 Project Standard 2021 Project Professional 2019 Project Standard 2019 Project Professional 2016 Project Standard 2016

Data Type    Number

Entry Type    Calculated

Description    The Task Outline Number field contains the number that represents the associated task's position in the hierarchical outline structure. The task outline number is similar to a work breakdown structure (WBS) code, except that the task outline number is automatically entered by Project.

How Calculated    Project assigns the assignment's outline number according to the associated task's sequence and outline level in the project outline hierarchy. The first task has an outline number of 1. The subtask that appears directly under that first summary task has an outline number of 1.1. The next subtask on the same level has an outline number of 1.2. The first subtask of that subtask has an outline number of 1.2.1. A task with an outline number of 7.2 indicates that it's the second subtask under the seventh top-level task.

Best Uses    Add the Task Outline Number field to the Resource Usage view when you want to display the position of an assignment's task within the project's outline structure. If you use the outline numbers as WBS codes, this can help you identify tasks by number.

Example    When reporting on assignment progress, you prefer to use the outline numbers rather than the task names. You add the Task Outline Number field to the Resource Usage view to see the outline numbers.

Remarks    The Task Outline Number field is available only in the Resource Usage view, and not in the Task Usage view.

Reikia daugiau pagalbos?

Norite daugiau parinkčių?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.