Applies ToKlien Desktop Project Online Project Professional 2021 Project Standard 2021 Project Professional 2019 Project Standard 2019 Project Professional 2016 Project Standard 2016

The baseline budget cost fields (Baseline1 Budget Cost through Baseline10 Budget Cost) store the originally planned budget cost amounts for cost resources that are specifically identified as budget resources. The Baseline1 Budget Cost field stores budget cost for tasks, resources, or assignments saved with Baseline 1. Similarly, the Baseline2 Budget Cost through Baseline10 Budget Cost fields store planned budget cost for Baselines 2 through Baseline 10.

Budget resources are assigned only to the project summary task. Budget cost can be entered or reviewed at the project summary task's assignment level, or rolled up to the project summary task level. The Baseline1-10 Budget Cost fields show the total planned person-hours scheduled for a task, resource, or assignment. The timephased versions of these fields show these same person-hours distributed over time.

There are several categories of Baseline1-10 Budget Cost fields.

Baseline1-10 Budget Cost (task fields)

Data Type    Currency

Entry Type    Calculated or entered

How Calculated    When you assign a cost resource that is a budget resource to a project summary task, and then enter cost for the assignment in either the Task Usage or Resource Usage view.

The Baseline1-10 Budget Cost fields contain $0.00 until you set a baseline for the project. As soon as you save a baseline, the total budget cost is copied into the corresponding baseline budget cost field for the task. The baseline budget cost field that is used (for example, Baseline3 Budget Cost) depends on which baseline was saved (for example, Baseline 3).

Best Uses    In a task sheet, show the project summary task and add one of the Baseline1-10 Budget Cost fields and the Budget Cost field to compare the baseline budget cost against the currently scheduled budget cost. You might also want to compare the budget cost of one baseline against another. Reviewing the variances, you can see how the budget costs are changing throughout the life of the project.

Example    At the start of your project two months ago, you saved a project baseline. A month ago, the scope of your project changed, and you saved a second baseline with Baseline 1. Since then, you've made further adjustments and have saved a third baseline with Baseline 2. Now you want to compare the Baseline2 Budget Cost field with the current Budget Cost field. In the Task Sheet, you show the project summary task, and then add both the Baseline2 Budget Cost field and the Budget Cost field.

Remarks    The Baseline1-10 Budget Cost fields show information for cost resources, but not for work resources or material resources. To see overall baseline budget work information for work or material resources that have been assigned to the project summary task, add the appropriate Baseline1-10 Budget Work field to a task sheet.

To show the project summary task, on the Tools menu, click Options. On the View tab, select the Show project summary task check box.

To save a baseline plan, on the Tools menu, point to Tracking, and then click Set Baseline. Select the baseline you want—Baseline or Baseline 1 through Baseline 10. This copies the current value of the Budget Cost field into the corresponding Baseline Budget Cost field.

After you save a baseline, you can still edit baseline budget cost. However, edited baseline values do not cause any recalculation of baseline budget cost fields. The purpose of saving a baseline is to capture a "snapshot" of the project plan at a moment in time. Editing baseline values can change the integrity of your information and result in misleading conclusions from variance analyses.

Baseline1-10 Budget Cost (resource fields)

Data Type    Currency

Entry Type    Calculated or entered

How Calculated    When you assign a cost resource that is a budget resource to a project summary task, and then enter a cost for the assignment in either the Task Usage or Resource Usage view.

The Baseline1-10 Budget Cost fields contain $0.00 until you set a baseline for the project. As soon as you save a baseline, the total budget cost is copied into the corresponding baseline budget cost field for the resource. The baseline budget cost field that is used (for example, Baseline3 Budget Cost) depends on which baseline was saved (for example, Baseline 3).

Best Uses    In a resource sheet, add one of the Baseline1-10 Budget Cost fields and the Budget Cost field to compare the baseline budget cost against the currently scheduled budget cost. You might also want to compare the budget cost of one baseline against another. Reviewing the variances, you can see how the budget costs are changing throughout the life of the project.

Example    At the start of your project two months ago, you saved a project baseline. A month ago, the scope of your project changed, and you saved a second baseline with Baseline 1. Since then, you've made further adjustments and have saved a third baseline with Baseline 2. Now you want to compare the Baseline2 Budget Cost field with the current Budget Cost field. In the Resource Sheet, you show the project summary task, and then add both the Baseline2 Budget Cost field and the Budget Cost field.

Remarks    The Baseline1-10 Budget Cost fields show information for cost resources, but not for work resources or material resources. To see overall baseline budget work information for work or material resources that have been assigned to the project summary task, add the appropriate Baseline1-10 Budget Work field to a resource sheet.

To save a baseline plan, on the Tools menu, point to Tracking, and then click Set Baseline. Select the baseline you want—Baseline or Baseline 1 through Baseline 10. This copies the current value of the Budget Cost field into the corresponding Baseline Budget Cost field.

After you save a baseline, you can still edit baseline budget cost. However, edited baseline values do not cause any recalculation of baseline budget cost fields. The purpose of saving a baseline is to capture a "snapshot" of the project plan at a moment in time. Editing baseline values can change the integrity of your information and result in misleading conclusions from variance analyses.

Baseline1-10 Budget Cost (assignment fields)

Data Type    Currency

Entry Type    Calculated or entered

How Calculated    When you assign a cost resource that is a budget resource to a project summary task, and then enter cost for the assignment in either the Task Usage or Resource Usage view.

The Baseline1-10 Budget Cost fields contain $0.00 until you set a baseline for the project. As soon as you save a baseline, the total budget cost is copied into the corresponding baseline budget cost field for the assignment. The baseline budget cost field that is used (for example, Baseline3 Budget Cost) depends on which baseline was saved (for example, Baseline 3).

Best Uses    In the Task Usage or Resource Usage view, add one of the Baseline1-10 Budget Cost fields and the Budget Cost field to compare the baseline budget cost against the currently scheduled budget cost. You might also want to compare the budget cost of one baseline against another. Reviewing the variances, you can see how the budget costs are changing throughout the life of the project.

Example    At the start of your project two months ago, you saved a project baseline. A month ago, the scope of your project changed, and you saved a second baseline with Baseline 1. Since then, you've made further adjustments and have saved a third baseline with Baseline 2. Now you want to compare the Baseline2 Budget Cost field with the current Budget Cost field. In the Task Usage view, you show both the Baseline2 Budget Cost column and the Budget Cost column in the sheet portion of the view.

Remarks    The Baseline1-10 Budget Cost fields show information for cost resources, but not for work resources or material resources. To see overall baseline budget work information for work or material resources that have been assigned to the project summary task, add the appropriate Baseline1-10 Budget Work field to the Task Usage or Resource Usage view.

To save a baseline plan, on the Tools menu, point to Tracking, and then click Set Baseline. Select the baseline you want—Baseline or Baseline 1 through Baseline 10. This copies the current value of the Budget Cost field into the corresponding Baseline Budget Cost field.

After you save a baseline, you can still edit baseline budget cost. However, edited baseline values do not cause any recalculation of baseline budget cost fields. The purpose of saving a baseline is to capture a "snapshot" of the project plan at a moment in time. Editing baseline values can change the integrity of your information and result in misleading conclusions from variance analyses.

Baseline1-10 Budget Cost (task-timephased fields)

Data Type    Currency

Entry Type    Calculated or entered

How Calculated    When you assign a cost resource that is a budget resource to a project summary task, and then enter cost for the assignment in either the Task Usage or Resource Usage view.

The Baseline1-10 Budget Cost fields contain $0.00 until you set a baseline for the project. As soon as you save a baseline, this value is copied into the corresponding Baseline1-10 Budget Cost assignment-timephased field. The baseline budget cost field that is used (for example, Baseline3 Budget Cost) depends on which baseline was saved (for example, Baseline 3).

Best Uses    In the Task Usage view, click Detail Styles on the Format menu. To show the Baseline1-10 Budget Cost field in the timesheet portion of the view, move the appropriate Baseline1-10 Budget Cost field to the Show these fields box. This shows the breakdown of baseline budget cost for the project summary task spread out over time. If you also show the Budget Cost field in the view, you can compare the originally planned timephased budget cost against the currently scheduled budget cost.

Example    At the start of your project two months ago, you saved a project baseline. A month ago, the scope of your project changed, and you saved a second baseline with Baseline 1. Since then, you've made further adjustments and have saved a third baseline with Baseline 2. Now you want to compare the timephased Baseline2 Budget Cost field with the current Budget Cost field on the project summary task. In the Task Usage view, you add both the Baseline2 Budget Cost field and the Budget Cost field to the timesheet portion of the view.

Remarks    The Baseline1-10 Budget Cost fields show information for cost resources, but not for work resources or material resources. To see baseline timephased budget work information for work or material resources that have been assigned to the project summary task, add the appropriate Baseline1-10 Budget Work field to the timesheet portion of the Task Usage view.

To save a baseline plan, on the Tools menu, point to Tracking, and then click Set Baseline. Select the baseline you want—Baseline or Baseline 1 through Baseline 10. This copies the current value of the Budget Cost field into the corresponding Baseline Budget Cost field.

After you save a baseline, you can still edit baseline budget cost. However, edited baseline values do not cause any recalculation of baseline budget cost fields. The purpose of saving a baseline is to capture a "snapshot" of the project plan at a moment in time. Editing baseline values can change the integrity of your information and result in misleading conclusions from variance analyses.

Baseline1-10 Budget Cost (resource-timephased fields)

Data Type    Currency

Entry Type    Calculated or entered

How Calculated    When you assign a cost resource that is a budget resource to a project summary task, and then enter cost for the assignment in either the Task Usage or Resource Usage view.

The Baseline1-10 Budget Cost fields contain $0.00 until you set a baseline for the project. When you then save a project baseline, this value is saved in the Baseline1-10 Budget Cost resource-timephased field. The baseline budget cost field that is used (for example, Baseline3 Budget Cost) depends on which baseline was saved (for example, Baseline 3).

Best Uses    In the Resource Usage view, click Detail Styles on the Format menu. Show the appropriate Baseline1-10 Budget Cost field in the timesheet portion of the view to review the planned budget cost spread out over time. If you add the Budget Cost field as well, you can compare your original plan against the currently scheduled budget costs.

Example    At the start of your project two months ago, you saved a project baseline. A month ago, the scope of your project changed, and you saved a second baseline with Baseline 1. Since then, you've made further adjustments and have saved a third baseline with Baseline 2. Now you want to compare the timephased Baseline2 Budget Cost field with the current Budget Cost field by cost resource on the project summary assignment. In the Resource Usage view, you show the project summary task, and then add both the Baseline2 Budget Cost field and the Budget Cost field.

Remarks    The Baseline1-10 Budget Cost fields show information for cost resources, but not for work resources or material resources. To see baseline timephased budget work information for work or material resources that have been assigned to the project summary task, add the appropriate Baseline1-10 Budget Work field to the timesheet portion of the Resource Usage view.

To save a baseline plan, on the Tools menu, point to Tracking, and then click Set Baseline. Select the baseline you want—Baseline or Baseline 1 through Baseline 10. This copies the current value of the Budget Cost field into the corresponding Baseline Budget Cost field.

After you save a baseline, you can still edit baseline budget cost. However, edited baseline values do not cause any recalculation of baseline budget cost fields. The purpose of saving a baseline is to capture a "snapshot" of the project plan at a moment in time. Editing baseline values can change the integrity of your information and result in misleading conclusions from variance analyses.

Baseline1-10 Budget Cost (assignment-timephased fields)

Data Type    Currency

Entry Type    Calculated or entered

How Calculated    When you assign a cost resource that is a budget resource to a project summary task, and then enter a cost for the assignment in either the Task Usage or Resource Usage view.

The Baseline1-10 Budget Cost fields contain $0.00 until you set a baseline for the project. When you then save a project baseline, the timephased budget costs are copied into the corresponding Baseline1-10 Budget Cost assignment-timephased field. The baseline budget cost field that is used (for example, Baseline3 Budget Cost) depends on which baseline was saved (for example, Baseline 3).

Best Uses    In the Task Usage or Resource Usage view, click Detail Styles on the Format menu. To show the Baseline1-10 Budget Cost field in the timesheet portion of the view, move the appropriate Baseline1-10 Budget Cost field to the Show these fields box. You can now review the selected baseline for budget cost. If you also add the Budget Cost field, you can compare your selected baseline against the currently scheduled budget costs. You might also want to compare the budget cost of one baseline against another.

Example    At the start of your project two months ago, you saved a project baseline. A month ago, the scope of your project changed, and you saved a second baseline with Baseline 1. Since then, you've made further adjustments and have saved a third baseline with Baseline 2. Now you want to compare the assignment-timephased Baseline2 Budget Cost field with the current Budget Cost field. In the Task Usage view, you show both the Baseline2 Budget Cost column and the Budget Cost column in the timesheet portion of the view.

Remarks    The Baseline1-10 Budget Cost fields show information for cost resources, but not for work resources or material resources. To see baseline timephased budget work information for work or material resources that have been assigned to the project summary task, add the appropriate Baseline1-10 Budget Work field to the timesheet portion of the Task Usage or Resource Usage view.

To save a baseline plan, on the Tools menu, point to Tracking, and then click Set Baseline. Select the baseline you want—Baseline or Baseline 1 through Baseline 10. This copies the current value of the Budget Cost field into the corresponding Baseline Budget Cost field.

After you save a baseline, you can still edit baseline budget cost. However, edited baseline values do not cause any recalculation of baseline budget cost fields. The purpose of saving a baseline is to capture a "snapshot" of the project plan at a moment in time. Editing baseline values can change the integrity of your information and result in misleading conclusions from variance analyses.

Perlu bantuan lainnya?

Ingin opsi lainnya?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.