Applies ToKlijent za računala za Project Online Project Standard 2024 Project Professional 2021 Project Standard 2021 Project Professional 2019 Project Standard 2019 Project Professional 2016 Project Standard 2016 Project Professional 2013 Project Standard 2013

You can quickly update your project's tasks to 100% complete or the scheduled percent complete.

For example, your project is going well and most of your tasks are on track. Rather than updating each task in your project daily, you update the tasks to their scheduled percent complete weekly, and then modify the percent complete for those tasks that are either behind or ahead of schedule.

Quickly update tasks to 100% complete

If you have tasks in your project that have been completed as scheduled, you can quickly update them all to 100% percent complete for the current date, a status date, or a date that you specify.

Update tasks to 100% complete for the current or status date

  1. On the Task tab, in the View group, choose Gantt Chart.

  2. Hold CTRL and select each of the tasks in the list that you want to update.

    Tip: If the tasks that you want to update are listed consecutively, you can select the first task, hold SHIFT, and then select the last task to select the series.

  3. In the Schedule group, choose 100% Complete.

    100 % Complete

Update tasks to 100% complete for a specific date

When you perform this procedure, previously entered percentage of completion values for tasks with finish dates earlier than the complete-through date are replaced by 100%.

  1. On the Task tab, in the View group, choose Gantt Chart.

  2. To update specific tasks, hold CTRL and select each task in the list. You can select up to 10 tasks.

    Tip: If the tasks that you want to update are listed consecutively, you can select the first task, hold SHIFT, and then select the last task to select the series. If you want to update all tasks in the list, you do not need to select the tasks.

  3. On the Project tab, in the Status, group, choose Update Project.

  4. In the Update Project dialog box, select Update work as complete through, and then type or select the date through which you want progress updated.

    Important: If you don't specify a date, Project uses the current or status date.

  5. Select Set 0% or 100% complete only.

  6. If you are updating specific tasks, select Selected Tasks. If you are updating all tasks in the project, select Entire Project.

  7. Choose OK.

Quickly update tasks to scheduled percent complete

If you have several tasks in your project that are currently on schedule or were completed on schedule, you can update the scheduled percent complete for the current date, a status date, or a date that you specify.

Update tasks to scheduled percent complete for the current or status date

  1. On the Task tab, in the View group, choose Gantt Chart.

  2. Hold CTRL and select each of the tasks in the list that you want to update.

    Tip: If the tasks that you want to update are listed consecutively, you can select the first task, hold SHIFT, and then select the last task to select the series.

  3. In the Schedule group, choose Mark on Track.

Update tasks to scheduled percent complete for a specific date

  1. On the Task tab, in the View group, choose Gantt Chart.

  2. If you want to update only specific tasks, hold CTRL and select each of the tasks in the list.

    Tip: If the tasks that you want to update are listed consecutively, you can select the first task, hold SHIFT, and then select the last task to select the series. If you want to update all tasks in the list, you do not need to select the tasks.

  3. On the Project tab, in the Status, group, choose Update Project.

  4. In the Update Project dialog box, choose Update work as complete through, and then type or select the date through which you want progress updated.

  5. Select Set 0% - 100% complete.

  6. If you are updating specific tasks, select Selected Tasks. If you are updating all tasks in the project, select Entire Project.

Potrebna vam je dodatna pomoć?

Želite dodatne mogućnosti?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.