Applies ToKlijent za računala za Project Online Project Professional 2021 Project Standard 2021 Project Professional 2019 Project Standard 2019 Project Professional 2016 Project Standard 2016

Data Type    Date

Entry Type    Calculated

Description    The Complete Through field shows the progress of a task on the Gantt Chart, indicating the point up to which actuals have been reported for the task. This field is available only in the Bar Styles dialog box and is represented as a bar on the Gantt Chart.

How Calculated    When you use the Complete Through field on a bar on the Gantt Chart, Microsoft Project draws a graphical representation of the task's completion percentage value. Therefore, on the Gantt Chart, the bar indicates the date through which the task is complete.

Best Uses    Add the Complete Through field to a Gantt bar when you want to indicate graphically on the Gantt Chart the point up to which actual work has been reported for the task.

Example    You want to view graphically how much actual work has been done on your project. On the Gantt Chart, you add the Complete Through Gantt bar to show the date up to which tasks are completed. For example, the "Develop estimate" task is a two-day task that starts on Friday and ends on Monday. The task is marked 50 percent complete. On the Gantt Chart, the Complete Through bar runs from the task start date and time on Friday through the Complete Through date and time of Monday at 8:00 A.M.

Remarks    You can set the Complete Through bar on the Gantt Chart in the Bar Styles dialog box.

By default, the progress bar uses the Complete Through field on the Gantt Chart.

Potrebna vam je dodatna pomoć?

Želite dodatne mogućnosti?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.