The Committed Planned End Date field specifies the finish date of the project as committed to in a Portfolio Selection Scenario during resource constraint analysis.

Data Type    Date

Entry Type    Calculated

Best Uses    By working through a resource constraint analysis as part of a Portfolio Selection Scenario, you can adjust planned project dates to accommodate resource availability within a portfolio. You can save multiple Portfolio Selection Scenarios, including various models for planned start and finish dates, for further analysis. After a Portfolio Selection Scenario is committed, the planned end date is saved in the Committed Planned End Date field for each project.

You can add the Committed Planned End Date field to Project Center views or project field Web Parts for review by project and portfolio stakeholders. Individual project managers can adjust their project dates to reflect the values in the Committed Planned End Dates fields.

Example    As a result of working through the Portfolio Strategy process, you have committed to complete implementation of the “Develop SOX-compliant auditing mechanism” project by January 30, 2012. You add the Committed Planned End Date field to a Project Center view for the benefit of the responsible stakeholders and project managers.

Remarks     In Project Web App you can add this field to a Project Center summary view, for example.

Kas vajate veel abi?

Kas soovite rohkem valikuvariante?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.