Applies ToProject Online Desktop Client Project Standard 2024 Project Professional 2021 Project Standard 2021 Project Professional 2019 Project Standard 2019 Project Professional 2016 Project Standard 2016 Project Professional 2013 Project Standard 2013

If you find that your organization is not using a specific calendar in Project, delete it!

  1. Click File > Info > Organizer.

    Organize Global Template

  2. Click the Calendars tab.

    Calendars tab

  3. Choose the calendar you want to delete, and then Click Delete.

    Delete button on the Calendars tab

What else can I do with calendars?

Project enables you to fine-tune scheduling using multiple calendars. If you understand how they all work together, it's easier to plan for how your project's dates will be impacted. Here are a few more articles you might find helpful in building a more accurate picture of the working and nonworking days in your organization.

PROJECTS Set the general working days and times for a project Create a new base calendar Add a holiday to the project calendar

TASKS Add a calendar to a task

RESOURCES Set a unique schedule for a specific resource Add a resource's vacation time Change resource availability without using a calendar

Need more help?

Want more options?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.