By default, the start date for all new projects is the current date. Of course, you can change this to a different start time. You can also set the project to be scheduled from a finish date.
Tip: Project management Schedule your project from a start time if you can. Even if you know the date by which a project must be complete, scheduling from a start date gives you the maximum amount of flexibility.
Schedule your project start date or finish date
-
Select Project > Project Information.
-
In the Schedule from list, pick Project Start Date or Project Finish Date.
-
In the Start date or Finish date box, enter the date that you want to schedule from.
Tip |
Explanation |
---|---|
Choose only one scheduling method |
A project can only be scheduled from the start date or from the finish date at any one time. It cannot be scheduled from both dates simultaneously. |
Move the start time of a project |
You can change the project start date or finish date whenever you want to, even after you build the project plan. Select Project > Move Project. When you move a project, you can decide whether you want Project to also move dates on actual work performed. To have more control over how actual and uncompleted parts of tasks move, use the Project Update feature before you move it. Select Project > Update Project, and then select the Reschedule uncompleted work to start after option. Now, set a time in the future after which uncompleted work can be scheduled; actual dates on tasks will not move. Once you've done that, you can use the Move Project feature. |
Consider scheduling from a finish date |
You might want to schedule from a finish date in these cases:
|
What happens when Project schedules from a finish date? |
|
Look out for date constraints |
If the finish date doesn't change after you change the start date, then one or more tasks may have a date constraint applied. Review the constraints in your plan to make sure that they are all necessary and appropriate. To view a task's constraints, right-click on the task, select Information, and then select the Advanced tab. |
Look out for actual progress reported on tasks |
If the start date doesn't change after you change the finish date, one or more tasks may either have actual progress reported or have a date constraint applied. Review the constraints in your plan to make sure that they are all necessary and appropriate. To view a task's constraints, right-click on the task, select Information, and then select the Advanced tab. |