Applies ToНастолен клиент на Project Online Project Professional 2024 Project Standard 2024 Project Professional 2021 Project Standard 2021 Project Professional 2019 Project Standard 2019 Project Professional 2016 Project Standard 2016

The Cost Variance assignment fields show the difference between the baseline cost and total cost for a task, resource, or assignment. The total cost is the current estimate of costs based on actual costs and remaining costs.

There are several categories of Cost Variance fields.

Data Type    Currency

Cost Variance (task field)

Entry Type    Calculated

How Calculated    Microsoft Office Project calculates the cost variance as follows:

Cost Variance = Cost - Baseline Cost

Best Uses    Add the Cost Variance field to a task sheet when you want to see whether you're under, over, or exactly within your budget for a task. During a project, use this field to assess budgetary performance to date. At the end of a project, use this field to help with cost analysis and future project planning.

Example    The baseline cost for a task is $500 because you had originally estimated that it would take your $50 per hour resource 10 hours to complete. If your resource only takes 5 hours to complete the task, the baseline cost is $500 and the cost is updated to $250. Therefore, the cost variance shows -$250, indicating that you're under budget on the task by $250.

Remarks    If the cost variance is negative, the cost for the task is currently under the budgeted, or baseline, amount. If the cost variance is positive, the cost for the task is currently over budget. When the task is complete, this field shows the difference between baseline costs and actual costs.

Cost Variance (resource field)

Entry Type    Calculated

How Calculated    Microsoft Office Project calculates the cost variance as follows:

Cost Variance = Cost - Baseline Cost

Best Uses    Add the Cost Variance field to a resource view when you want to see whether you're under, over, or exactly within your budget for a resource. During a project, use this field to assess budgetary performance to date. At the end of a project, use this field to help with cost analysis and future project planning.

Example    Your baseline cost for a resource is $5,000, and your cost (total cost) is $4,500. Your cost variance is -$500, meaning you're $500 under budget.

Remarks    If the cost variance is negative, the cost for the resource is currently under the budgeted, or baseline, amount. If the cost variance is positive, the cost for the resource is currently over budget.

Cost Variance (assignment field)

Entry Type    Calculated

How Calculated    Microsoft Office Project calculates the cost variance as follows:

Cost Variance = Cost - Baseline Cost

Best Uses    Add the Cost Variance field to the sheet portion of the Task Usage or Resource Usage view when you want to see whether you're under, over, or exactly within your budget for an assignment. During a project, use this field to assess budgetary performance to date. At the end of a project, use this field to help with cost analysis and future project planning.

Example    If your baseline cost for an assignment is $500, and your cost (total cost) is $400, your cost variance is -$100, meaning you're $100 under budget.

Remarks    If the cost variance is negative, the cost for the assignment is currently under the budgeted, or baseline, amount. If the cost variance is positive, the cost for the assignment is currently over budget. When the assignment is complete, this field shows the difference between baseline costs and actual costs.

Нуждаете ли се от още помощ?

Искате ли още опции?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.