Applies ToНастолен клиент на Project Online Project Standard 2024 Project Professional 2021 Project Standard 2021 Project Professional 2019 Project Standard 2019 Project Professional 2016 Project Standard 2016 Project Professional 2013 Project Standard 2013

When you assign or remove people from a task, Project lengthens or shortens the duration of the task based on the number of resources that are assigned to it, but Project does not change the total work for the task. This is called effort-driven scheduling and is the setting Project typically uses when you assign resources to tasks.

  1. Double-click the task.

  2. In the Task Information box, click the Advanced tab.

  3. Uncheck the Effort driven check box.You can add the Effort Driven column to a sheet view. Right-click a column heading and then click Insert Column.

Although effort-driven scheduling works most of the time, you may want to change this to more accurately reflect what happens when resources are added or removed for a particular task. For example, you may want to see the total work increase as you add more people to a task.

Here are some exceptions to watch out for when you change the effort-driven setting.

Exception

Explanation

First assignment

Effort-driven calculations apply only after resources are initially assigned to the task. After the first resources are assigned, the work value doesn't change as new resources are assigned or removed from the same task.

Fixed work tasks

You can’t remove effort-driven scheduling from fixed-work tasks. Fixed work tasks do not have flexible work values, and are therefore always effort-driven.

Fixed unit tasks

If the assigned task type is fixed units, assigning additional resources shortens the duration of the task.

Fixed duration tasks

If the assigned task type is fixed duration, assigning additional resources decreases the individual unit values for resources.

Summary tasks

Summary tasks and inserted projects can’t be set to effort-driven.

Inserted projects

Inserted projects can’t be set to effort-driven.

Нуждаете ли се от още помощ?

Искате ли още опции?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.